# Scenarios

A Scenario is a self-contained scheduling environment where all configuration, orders, and schedule data are stored. Use scenarios to create production schedules, run "what-if" analyses, or model alternative plans before publishing to the organisation.

## Navigation

***Scheduler*** > ***Scenario***

The Scenario screen displays a Kanban board showing all scenarios organised by status.

## Scenario Statuses

Scenarios follow a lifecycle through four stages on the Kanban board:

| Status        | Description                                                                                                                          |
| ------------- | ------------------------------------------------------------------------------------------------------------------------------------ |
| **Draft**     | Initial state after creation. Draft scenarios are private to the creator and can be used to model "what-if" analyses without sharing |
| **Proposed**  | Scenarios ready for review by other users. Multiple proposed scenarios can exist simultaneously for comparison                       |
| **Published** | The active schedule being executed by the organisation. Moving a scenario to Published sends an email notification to other users    |
| **Complete**  | Finished scenarios filed for reference. Can be deleted from here if no longer needed                                                 |

{% hint style="info" %}
Only move a scenario from Draft once you are ready for other users to view and interact with it. The controlled progression ensures that only reviewed and approved schedules become active.
{% endhint %}

## Creating a Scenario

1. Click the **+** button on the Scenario Kanban board.
2. Enter a **Name** and **Description** for the scenario.
3. Set the **Start Date** — this defines the beginning of the planning horizon.
4. Click **Create**.

The new scenario appears in the **Draft** column.

<figure><img src="/files/yurMCg6nIvuT0o2f9490" alt=""><figcaption></figcaption></figure>

## Scenario Actions

Click on the three dot more buttons:

| Action        | Description                                                                                                                                                               |
| ------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------- |
| **Open**      | Opens the scenario to view and edit the schedule                                                                                                                          |
| **Clone**     | Copies the entire scenario configuration, including orders, previously scheduled orders, tasks, and all settings                                                          |
| **Delete**    | Permanently removes the scenario (admin privileges required). A confirmation dialog warns that this cannot be reversed                                                    |
| **Make Live** | Sets this scenario as the Live Scenario. Only one scenario can be live at a time. Orders in the live scenario are automatically synchronised to TilliT Digital Operations |

<figure><img src="/files/WxD9iob1ma4ML7NAVPDh" alt=""><figcaption></figcaption></figure>

## Cloning a Scenario

Cloning duplicates an existing scenario with all its data, including:

* Orders and previously scheduled orders
* Tasks
* All configuration settings

Cloned scenarios function identically to any other scenario and can move through all workflow stages.

## Using Template Scenarios

We recommend creating a **Template Scenario** that serves as the foundation for all new scenarios. The template should contain clean, validated, and up-to-date configuration based on accurate master data from your source systems, including:

* Equipment resources
* Personnel
* Operations
* Availability (shifts)
* Materials

Since this foundational data typically does not change daily, starting each new scenario from the template ensures you begin with accurate, consistent information.

## Naming Best Practices

A well-structured naming convention helps organise and identify scenarios. Include:

* A name that reflects the scenario's objective
* The date range or time horizon the scenario addresses

**Examples:**

* "Weekly Schedule 12th April - Reduced Shifts" — a weekly schedule exploring reduced staffing levels
* "Standard 24/5 Template" — a template for regular 24-hour, 5-day operations